Center Street Improvements Project
Purpose
Reconstruction and beautification of Center Street between Main Street and 800 East.
Project Description
This project will complete curb, gutter and sidewalk along the south side of Center Street, install traffic control devices at key intersections along Center Street, and reconstruct the pavement section of Center Street between Main Street and 800 East.
Work Schedule
- Construction of the project began the first week in June 2024, just after the completion of the school year.
- Asphalt paving, with the exception of the 400 East intersection was completed before school starting (August 15).
- Curb, gutter, sidewalk and other concrete improvements continue and are anticipated to be finished Fall 2024.
- Roundabout construction at 400 East is anticipated to be finished Fall 2024.